Were you able to see if the transformer has been placed yet? That would be the only thing to hold up progress. Looks like the have some light standards to still be installed.
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
Were you able to see if the transformer has been placed yet? That would be the only thing to hold up progress. Looks like the have some light standards to still be installed.
I spoke to the electrician doing final ground installation and he said that Monday, December 28th would be the inspection date for the Fresno SC station. He contemplated maybe another 30 days until it goes live.
View attachment 106647View attachment 106648View attachment 106649View attachment 106650View attachment 106651View attachment 106652
The temporary fence surrounding the Fresno Supercharger is gone. Here are six photographs taken earlier today showing the ten charging stalls, "Tesla Vehicle Charging" sign at all ten slots, the wired pad awaiting the transformer, the interior of the charging enclosure and a view of the charger enclosure. I really like the design of the charging enclosure.
The cables on the pods are not attached. The dumpster, outhouse and the storage container are still present adjacent to the charging stalls.
There is a slight dip in the pavement about two feet away from the curb that is perpendicular to the parking places.
I do not know if the city inspector has signed off on the building permit nor when the transformer will be delivered.
Let's hope this opens in the next couple of weeks!
If you have the CHAdeMO adapter, there are two free L3s at FSU. That came in handy on my trip to Yosemite from SoCal over the holidays. There are free L2s there too.