Yes, unless you drive into oncoming traffic, you can’t reach that Shell without leaving airport geofenceAre you sure about that?
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
Yes, unless you drive into oncoming traffic, you can’t reach that Shell without leaving airport geofenceAre you sure about that?
That is usually the case when a "pad mount" transformer is used, but this location will utilize the shorter lead "pole mount" transform banks. The utility company has already delivered the poles, so its in motion.What about the transformer? I heard that is the long pole in every installation
Once the contractor gets these “house lines” installed and inspected, CenterPoint will come out and make the connections, install the fuses, set the meter. Then Tesla commissioning.
The didn’t finish tying them in on the gear end before leaving. They do that before the city comes to make the pre-connection inspection, right?Once the contractor gets these “house lines” installed and inspected, CenterPoint will come out and make the connections, install the fuses, set the meter. Then Tesla commissioning.
The didn’t finish tying them in on the gear end before leaving. They do that before the city comes to make the pre-connection inspection, right?
Yeah, fence has been down at least a few days now. I can’t see anything left to do but wait for inspection sign off so they can tie into the transformersDrove by Saturday and most of the site clean up has been completed with just a few palatized wire spools to be picked up. Construction fence has been taken down and removed. Guessing an inspection is hanging out there?
Still Hanging as of Halloween Eve '23Main feeders still hanging as seen in Post #31