Don’t trust the site. The Design review Marco posted was approved in May. No building or electrical permits have been applied for relating to the SC. It doesn’t mean it isn’t happening, it’s just awaiting the next phase of the project. Once we see an actual building permit, electrical permit and dig ticket, then construction will be imminent. Until those happen, we just have to wait and see. I wish people like Marco would point out that a Design Review is not a building permit. It is just due diligence and sometimes even when approved, the project may get held up or even canceled for other reasons.