I can’t say for sure, but from the photo you posted the charging cables do not look like the thinner V3 type.They also said it would be a V3 supercharger but I’m not confident they knew what the difference.
Took this photo on May 24. I called the construction company and they thought it would be done in another month. They also said it would be a V3 supercharger but I’m not confident they knew what the difference.
I drove through on Friday and they were working - I saw a concrete truck. I had my trailer connected so I didn’t bother to stop for photos. It sure looks close, though.
I will be driving through around 3:30am on 6/22. It would be nice not to have to drive down to Ukiah to backtrack to get to Ft. Bragg. crossing finger!!!!
On Tuesday I stopped by on my way to Rohnert Park from Eureka. Wiring work was being done on the charger cabinets. Yesterday all of the cabinets were closed, and the only work that I saw was a guy sweeping the lot in front of the Charge Point equipment. All of the work appeared to be done except final landscaping. The fences were still up though.
Did you see either a utility transformer (big green cabinet with cooling fins) or an empty concrete pad awating one? That's often one of the last pieces of equipment to arrive.
sooo close. I was going to ask schedule but they drove away for lunch as I stopped : <
looks like just fence and signs? they had the pedestal tops all open on the SC's. will be there Thursday and Saturday again...
tranny in back..double bollard protected View attachment 423311 View attachment 423312