Solar Tesla Roof Install - 15.6 KWH: Nov 9th - Nov 18th (Complete)
PowerWall+ x 2: Nov 19th (Not Complete)
Had a relatively smooth experience with the Roof Install (will find out when we have more rain...)
Fun started when the PowerWall+ team came out using designs made in June, but were updated in Nov (new PV 72W panels and Backup Switch with PG&E using PowerWall+ instead of BGW2). There was suppose to be a scheduled MPU since my panel's bus doesn't handle the load required, which I thought the Friday team was doing, but there was some confusion. They installed the PW's, but now I'm waiting on Tesla to sub-contract the MPU upgrade (2-3 weeks out due to component shortage), then the PW team can come back out and finish the work from connecting PW's to the main panel. My Project Advisor has been somewhat responsive, but I expect I will be going through a lengthly process here on out.
My question is:
They are pushing the Backup Switch, which looks clean and saves on the re-wiring/space. Bonus is since my panel is exactly 3ft from the gas line, other than like-for-like work, it would've likely required some suboptimal wire planing for PG&E to approve.
I'm wondering if anyone in the East Bay (specifically Dublin/Freemont) area has had any experiences with the Backup Switch & PG&E specifically? Does Tesla install the Backup Switch and PG&E come out later to tag, or do I have to wait for yet another appointment to have PG&E & Tesla come out and install the Backup Switch? Still on the fence to push back on the BSW on ask for a BGW2 if it will save me a lot of headaches (and time).
I don't plan to pay a single $1 (ok $101) until a PTO application is made and I have a working system and we pass final inspection, but I'm trying to gauge my own expectations re: timing.
Also, if anyone who's gone through this process have any tidbits on whom to contact (both at Tesla / PG&E) etc. please DM me.
Thx.
PowerWall+ x 2: Nov 19th (Not Complete)
Had a relatively smooth experience with the Roof Install (will find out when we have more rain...)
Fun started when the PowerWall+ team came out using designs made in June, but were updated in Nov (new PV 72W panels and Backup Switch with PG&E using PowerWall+ instead of BGW2). There was suppose to be a scheduled MPU since my panel's bus doesn't handle the load required, which I thought the Friday team was doing, but there was some confusion. They installed the PW's, but now I'm waiting on Tesla to sub-contract the MPU upgrade (2-3 weeks out due to component shortage), then the PW team can come back out and finish the work from connecting PW's to the main panel. My Project Advisor has been somewhat responsive, but I expect I will be going through a lengthly process here on out.
My question is:
They are pushing the Backup Switch, which looks clean and saves on the re-wiring/space. Bonus is since my panel is exactly 3ft from the gas line, other than like-for-like work, it would've likely required some suboptimal wire planing for PG&E to approve.
I'm wondering if anyone in the East Bay (specifically Dublin/Freemont) area has had any experiences with the Backup Switch & PG&E specifically? Does Tesla install the Backup Switch and PG&E come out later to tag, or do I have to wait for yet another appointment to have PG&E & Tesla come out and install the Backup Switch? Still on the fence to push back on the BSW on ask for a BGW2 if it will save me a lot of headaches (and time).
I don't plan to pay a single $1 (ok $101) until a PTO application is made and I have a working system and we pass final inspection, but I'm trying to gauge my own expectations re: timing.
Also, if anyone who's gone through this process have any tidbits on whom to contact (both at Tesla / PG&E) etc. please DM me.
Thx.