I believe the sooner you can contact your local install team (or some customer in your area) the better you can assess the overall schedule. I suggest you start a thread (Or look through historical posts) specifically targeting your local market to make local connections. I did this in Houston and it helped me quite a bit!
Can anyone chime in on how long it took Tesla to supply a permit to their city/county? I've been waiting on this part of the process since 9/10. I called my advisor on 9/17 and actually got a hold of them for the first time, and they said they are waiting for someone to draw up the blueprints of the powerwall to submit with the permit.
This is something that’s going to be very location dependent because different jurisdictions have vastly different requirements for permits. In my case my city requires signed and sealed engineering drawings. I ordered on 5/12 and tesla finally applied for the permit on 5/29. Other jurisdictions don’t have such stringent requirements and it can take only a few days for tesla to request the permit.
And again, once the permit has been requested different locations will take different amounts of time to approve it. In my case my city approved the permit in just two business days, but I’ve seen people post that it took their permitting authority several weeks or longer to approve it.
A lot of cities and counties have permitting information online, so you may be able to go to their website and search for your address and see if tesla has applied for the permit yet. If not you can keep checking every now and then to see when it finally does appear, then you can watch it and see when it is approved.