Hey, so I received an email back from Mark, kinda surprised that I did and it's got a good bit of info in it. I've posted it below.
_______________________________________________________________________________________
"Hello,
I was hoping you might have some more detailed status on a couple EV charging sites. I’m looking for information on Indian Springs and Wendover. Do you have any information beyond the estimated completion date of May/February and what connections/levels will be at these sites?
Thank you,
Matt "
_________________________________________________________________________________________
"Hi Matt,
Sorry for the delay, been traveling all week, but thanks for the question!
Indian Springs – that project we have partnered with NV Energy on and the local site host is Terrible Herbst. The Terrible Herbst team is building a new gas station (they bought an old one and doing a demo/rebuild). The new site along with the EV charging equipment is currently slated to become operation Memorial Day weekend (May 2020). We haven’t formally updated our documents showing that as the formal request hasn’t come through, but that’s very likely here shortly.
Equipment: 2x BTCPower 50kW, CCS and CHAdeMO
W. Wendover – that project we have partnered with Wells Rural Electric Cooperative and the local site is the City. The project is at the City’s Welcome Center. The chargers were planned to be commissioned this week (though I’ve been traveling all week so haven’t heard the latest). They project won’t officially be finished for another few months as they are planning to build a shade structure to help protect the equipment. They are also in the process of getting the chargers networked – once that happens they should auto populate on sites like plugshare. So the general public should be able to use them in the next week or so (if things went to plan).
Equipment: haven’t seen the invoices yet, so some uncertainty. But plan is for 1x 50kW EFACEC QC45 that has both CCS and CHAdeMO. 1x either (1x 50kW EFACEC QC45 that has both CCS and CHAdeMO) or (level 2 charger) for a total of 2 chargers.
Hope this helps, let me know if you have any additional questions.
Thanks,
-Mark
Mark Brady
Nevada Governor’s Office of Energy
755 N. Roop St. Suite 202
Carson City, NV 89701
T: (775) 687-1850 x 7320
[email protected] "