Your entire basis is incorrect.@Jeremy3292 you think Crossville, TN supports 24 V3 chargers? This is more chargers than anywhere else in the state, and one of the largest in the region.
You can't see the forest for the trees.When the supply of Superchargers is limited, then there is most definitely such a thing as "too many" supercharges in an area.
Put those 8 chargers at the winery in Murfreesboro or Clarksville instead and I guarantee they get more usage.
The chargers at Buccees is the right move. They messed up by putting the chargers at the winery a year ago when they knew these chargers were coming at the same exit. That's the poor planning I was referring to.
The winery chargers were under construction circa June 2021 and came online Oct 15 2021. The nation wide agreement with Buc-ee's was established mid November 2021. All Buc-ee's installations happened quite quickly and I don't think anybody "knew" beforehand how fast things could happen with Buc-ee's on either a national or local scale. I've charged at the winery, and found it to be "adequate" but hours are sadly limited. Buc-ee's experience is far better and frankly in a different league.When the supply of Superchargers is limited, then there is most definitely such a thing as "too many" supercharges in an area.
Put those 8 chargers at the winery in Murfreesboro or Clarksville instead and I guarantee they get more usage.
The chargers at Buccees is the right move. They messed up by putting the chargers at the winery a year ago when they knew these chargers were coming at the same exit. That's the poor planning I was referring to.
Supercharger citing and timing is not an exact science. I'm sure many never make it through the location, agreement, permitting, utility, and other steps to become a supercharger; some take months others well over a year. When putting in 8 stalls, expanding to 12 or 16 is a small additional current cost and significantly cheaper than building an additional site later.It’s simple if you ignore all the other gaps that’s still exist that have zero chargers instead of this one now with one of the largest combined installations in the region. Checkout some of the massive gaps in the west and tell me Crossville needed 24 chargers before any of those.
The transformer is already in place and the conduits run, so it’s just a matter of running wires and then connecting power to the transformer. Should be quick!Construction has *really* got underway now. Photo attached.
View attachment 896364
You had a few details wrong, and I tried to fill in with some of the history. We're all on the same team here. Your input is appreciated; please continue to contribute.Thank you for the expert analysis TSLA Bull.
I was the one to report these chargers under construction yesterday. When I was….. at the Buc-ees
I regret ever saying something negative about Tesla on this forum. What was I thinking.
Great photo. It's looking to be coming on quickly.View attachment 896822
Pic from January 14, 2023.
Why do you say there is a limited supply of Superchargers?When the supply of Superchargers is limited, then there is most definitely such a thing as "too many" supercharges in an area.