BTW - The CHAdeMO adapter is currently at $600. When did that happen?
You are looking at Canadian prices.
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
BTW - The CHAdeMO adapter is currently at $600. When did that happen?
That's the price in Canadian dollars, which is displayed if you're on the webpage with Canada set as the location. Try looking at the US store page for it. It's still US$450. (If that link didn't take you to the US page, scroll down to the bottom and click on the flag to set the location)
Seven or eight months IIRC. The most aggravating part is the zero sense of urgency to get it back up and running coupled with absolutely no official explanations or projected time frame. Please correct me if I am wrong about the last part.
The transformer fire led to a massive finger pointing game and investigation, that's understandable. That appears to have been done, new equipment installed, electrical inspection passed, now what is the holdup?
If I go online and buy a CHAdeMO adapter right now, the supercharger station will be open tomorrow. BTW - The CHAdeMO adapter is currently at $600. When did that happen?
Not sure who’s fault it is for the delay. With the government and Tesla involved it could be anyone. I’m sure the fire gives lots of ammo to anyone that would rather it not be there.
Don’t understand why people expect a press release or personal communication? I don’t see that when a new gas station opens. It just sets up the expectations that then have to be managed.
I emailed that Sarah lady and I have received nothing back lol. So sad, 7 months closed! And they don't give a damn.
Not sure who’s fault it is for the delay. With the government and Tesla involved it could be anyone. I’m sure the fire gives lots of ammo to anyone that would rather it not be there.
Don’t understand why people expect a press release or personal communication? I don’t see that when a new gas station opens. It just sets up the expectations that then have to be managed.
ooh - building permit now reads "Finaled"
all the fees were paid 7/19
shown as Approved 7/24/2019 1:09 PM
So theoretically that should unlock the related electrical permit.
One step at a time . . . .
I’m really hoping that they get this fixed for 8/10.
Was there Sunday 8/4. Still not operational. Most pedestals have the "coming soon" cover.Has anyone been by the location in the last few day? Just curious...
Visited at 1000 for a fill up. Only problem was the majority of chargers were ICE. Hope the gas vehicle drivers made an honest mistake not realizing it’s open.