Hi all,
I wanted to share my timeline for my Tesla Solar install, as I'm seeing a number of horror stories on here, and ask a quick question. Overall I've been blown away by Tesla Solar, with one exception - how they communicate. The following is an example of my experience in the Denver metro area.
The system:
The timeline:
The question:
I've had my system set up for four days now (not a huge sample size), and in that time we've had direct sunlight and clear skies a number of times. My system has yet to generate above 4.3 kW. I'm not expecting to ever hit 8 kW, but I'm not getting close. My main concern is that some of the panels may not be hooked up correctly and aren't working.
I hope this post helps others in the future!
I wanted to share my timeline for my Tesla Solar install, as I'm seeing a number of horror stories on here, and ask a quick question. Overall I've been blown away by Tesla Solar, with one exception - how they communicate. The following is an example of my experience in the Denver metro area.
The system:
- 8.16 kW system
- No Powerwalls
- Estimated 11,288 kWh annual production (102% of my household needs)
The timeline:
- April 11 - Submitted the deposit online and upload the required photos. This was a Sunday and by the end of the day, I had a project manager texting me and an initial design. I agreed to the design and completed the finance set up that evening.
- April 15 - Tesla communicated that they had begun pulling permits. The permits from my city were issued by the end of the day.
- April 17 - I received approval from my HOA to continue and shared it with the Tesla team.
- April 21 - Everything on Tesla's side is ready to go and I call to schedule installation. I chose April 30.
- April 30 - Tesla team shows up on time. The crew works for Tesla Energy and is experienced, polite, and friendly. They even entertained my toddler's endless questions and showed him around the truck. I was blown away by their professionalism!
- May 5 - The system passes inspection.
- May 14 - I call the utility company to check on the status of my meter swap and receiving Permission to Operate. I'm told Tesla never submitted the final documents. Not good... I called my Tesla installation team (whose direct number I had) and they worked to get the paperwork submitted that day.
- May 19 - Xcel, my local utility company, replaced the meter and gives PTO (they actually turned the system on). We're up and running!
The question:
I've had my system set up for four days now (not a huge sample size), and in that time we've had direct sunlight and clear skies a number of times. My system has yet to generate above 4.3 kW. I'm not expecting to ever hit 8 kW, but I'm not getting close. My main concern is that some of the panels may not be hooked up correctly and aren't working.
- What sort of generation should I be expecting?
- How long should I wait before I contact Tesla?
I hope this post helps others in the future!