This new one is better. I’d be surprised if they keep the same last 6 digit numbering sequence though.
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
This new one is better. I’d be surprised if they keep the same last 6 digit numbering sequence though.
Once they are in full swing, yes. But will a ramp up of production, it will be hit or miss at the start.Will Chicago also get delivery from Austin ? Being Midwest region
Mine didn't move. I put on hold till April.Once they are in full swing, yes. But will a ramp up of production, it will be hit or miss at the start.
When did you order? Maybe you got moved from Jan to April as a placeholder until they recalculate for Austin. Mine got moved to June, no dates nothing, just June.
how were you able to put it on hold until then? only asking because i’d like to order now but also take delivery laterMine didn't move. I put on hold till April.
I packed order on Dec/19. Initial delivery estimate was "July". Around Jan/04 , EDD changed to Jan/16-Feb/10. So I have to put hold. Now wondering if I get Austin one.
Ah, if you ordered in Dec and you got a Jan EDD, assume you ordered a MYP. With the lower demand for a MYP and quicker delivery time, it sure if they will be produced in Austin or not. If they increased production facilities for MYP, it won’t be long before they will have a surplus.Mine didn't move. I put on hold till April.
I packed order on Dec/19. Initial delivery estimate was "July". Around Jan/04 , EDD changed to Jan/16-Feb/10. So I have to put hold. Now wondering if I get Austin one.
MY BLUE/white/induction. No MYPAh, if you ordered in Dec and you got a Jan EDD, assume you ordered a MYP. With the lower demand for a MYP and quicker delivery time, it sure if they will be produced in Austin or not. If they increased production facilities for MYP, it won’t be long before they will have a surplus.
Then that Jan had to be a car someone passed on. I would expect a June/July delivery date by default, for normal delivery timeMY BLUE/white/induction. No MYP
Yes. Someone passed on, likely would be. If Austin production goes to east coast then, what about Chicago ? Being in Midwest.Then that Jan had to be a car someone passed on. I would expect a June/July delivery date by default, for normal delivery time
I really think people need to take a deep breath on Giga Texas. It’s not like Monday they say go and then 1000 cars a week come out of that place and start shipping Tuesday. It’s going to be a series of walkthrough builds, training, QA holds and validation and proofing. Dozens of vehicles most kept internally. Maybe some released for a launch event in January. And then they will begin producing.My model Y EDD just changed this morning from 1/8-1/19 to 1/23-2/4. White on white no add ons and 8/18 order date. Giga Texas vehicle seems likely but you never know.
East of Mississippi. They keep saying east coast. Chicago will be seeing MY from AustinYes. Someone passed on, likely would be. If Austin production goes to east coast then, what about Chicago ? Being in Midwest.
I agree. The first few weeks will likely be built for insiders, employees, friends and family.I really think people need to take a deep breath on Giga Texas. It’s not like Monday they say go and then 1000 cars a week come out of that place and start shipping Tuesday. It’s going to be a series of walkthrough builds, training, QA holds and validation and proofing. Dozens of vehicles most kept internally. Maybe some released for a launch event in January. And then they will begin producing.
Based on traditional manufacturing ramp and what we know from Teslas history, IF and it’s a BIG IF, Austin starts production next week the realistic best case would be a few hundred cars shipped to customers in Feb. March and April on would be meaningful numbers (1.000+) and by June they should be pushing major ramp and stop shipping from Fremont to east coast.
I just don’t see logistically anything different. It just doesn’t work that way in automated manufacturing. Especially with something that has the complexity and safety requirements of a car. Much less the risk of a large recall.
Here is a projections YouTube based on Shanghai. We already know training has been going on for some time now, as has QA. Estimate is 500 cars a week at start. If I recall the projections correctI really think people need to take a deep breath on Giga Texas. It’s not like Monday they say go and then 1000 cars a week come out of that place and start shipping Tuesday. It’s going to be a series of walkthrough builds, training, QA holds and validation and proofing. Dozens of vehicles most kept internally. Maybe some released for a launch event in January. And then they will begin producing.
Based on traditional manufacturing ramp and what we know from Teslas history, IF and it’s a BIG IF, Austin starts production next week the realistic best case would be a few hundred cars shipped to customers in Feb. March and April on would be meaningful numbers (1.000+) and by June they should be pushing major ramp and stop shipping from Fremont to east coast.
I just don’t see logistically anything different. It just doesn’t work that way in automated manufacturing. Especially with something that has the complexity and safety requirements of a car. Much less the risk of a large recall.
Lots of assumptions in that video and then they use average a lot. 2000 cars a week in the last 2 weeks of March does a lot to raise the “average“ for the quarter. There’s also the whole when is start / start. Training may be ongoing, but production training hasn’t. We used to train on production lines and you could simulate, test, etc all day but until actual line production with ramp speeds and downstream holds and defects start happening you haven’t really trained.Here is a projections YouTube based on Shanghai. We already know training has been going on for some time now, as has QA. Estimate is 500 cars a week at start. If I recall the projections correct
I put mine on hold also. Ordered October 21. Said delivery was aug 22. Moved edd between Jan 21-feb28 of 22. Texted the person I worked with at the store to place the order and asked them to put it on hold. They said because my original delivery date was aug, they can put it on hold without any issues. It will come off hold in August 22.how were you able to put it on hold until then? only asking because i’d like to order now but also take delivery later
I had a long standing March-April EDD, then went to June last week. I am hoping this is because I am getting an Austin MY. Know a bunch of other eastern half of US people have also moved to June, most seemed to have had late Feb to April EDDLots of assumptions in that video and then they use average a lot. 2000 cars a week in the last 2 weeks of March does a lot to raise the “average“ for the quarter. There’s also the whole when is start / start. Training may be ongoing, but production training hasn’t. We used to train on production lines and you could simulate, test, etc all day but until actual line production with ramp speeds and downstream holds and defects start happening you haven’t really trained.
My only point is the people with late Jan and early Feb EDDs saying this means Austin if they start production next week…. there may be some lucky lottery winners, but no. They aren’t shifting EDDs for Jan / Feb based on Austin. And if you have an EDD of Jan 21-Feb 3, you are not getting an Austin build. They will not make the first car in Austin on Monday and start shipping out Wednesday or Thursday. It’s just not realistic.
I would agree the likelihood of a June Austin MY is much much higher than a Jan or Feb Austin MY.I had a long standing March-April EDD, then went to June last week. I am hoping this is because I am getting an Austin MY. Know a bunch of other eastern half of US people have also moved to June, most seemed to have had late Feb to April EDD
I’m sure you’re right about initial limited production and the first Austin VINs being ‘lottery winners’ (TBD if initial QA is good enough to feel like a lottery winner). It’s that hope of winning the lottery that keeps threads like this going.Lots of assumptions in that video and then they use average a lot. 2000 cars a week in the last 2 weeks of March does a lot to raise the “average“ for the quarter. There’s also the whole when is start / start. Training may be ongoing, but production training hasn’t. We used to train on production lines and you could simulate, test, etc all day but until actual line production with ramp speeds and downstream holds and defects start happening you haven’t really trained.
My only point is the people with late Jan and early Feb EDDs saying this means Austin if they start production next week…. there may be some lucky lottery winners, but no. They aren’t shifting EDDs for Jan / Feb based on Austin. And if you have an EDD of Jan 21-Feb 3, you are not getting an Austin build. They will not make the first car in Austin on Monday and start shipping out Wednesday or Thursday. It’s just not realistic.