My 232 day wait time has come to an end, picked up my car yesterday.
NON-Matrix / CCS / some gaps / 72% charged / 8 km odometer
Some panel gaps on front bumper, the driver side door is in too deep but the main annoying one is the interior trim on both front doors doesn't seem to be attached very well because it rattles a lot when closing the door. Was told to file a service request within 24hrs. Drives great.
Mine was one of the ECU missing cars and I actually saw the left over sticker glue around charging port.
A new software update (2022.11.101.1) was prompting to install immediately when I got in the car at the delivery center. Installed it later when I got home.
Here's my whole history for reference
Order Date Oct 15, 2021:EDD Mar 2022
Oct 19: 1st trade in offer (don't know when I cancelled it)
end of Oct: Apr
Oct 28: Jun
Oct 31: Feb 23 - Mar 23
early Nov: Mar 1 - Mar 29
Nov 19: Feb 9 - Mar 9
Jan 12: asked for an updated trade-in offer
Jan 13: received trade-in offer - don't know when I cancelled it
Jan 19: Jun
Jan 21: May 11 - Jun 8
Feb 1: Feb 24 - Mar 24
Feb 7: Order changed from SR+ to RWD
Feb 8: Feb 22 - Mar 8 (2 week window)
Feb 18: Mar 11 - Mar 31 (20 day window, 10 days in between)
Feb 26: Mar 14 - Mar 28 (2 week window, 8 days in between)
Mar 10: Apr 4 - May 2 (1 month window, 12 days in between)
Mar 13: Apr 13 - Apr 27 (2 week window, 3 days in between)
Mar 22: Apr 16 - May 14 (1 month window, 9 days in between)
Apr 4: went to Oakville Tesla, asked for info, they said "i shouldn't show you this screen" but you have a 'factory gate' date of Apr 24 (when it leaves the factory) and it'll get here around may 5.
Apr 13: May 3 - May 17 (2 week window, 22 days in between)
Apr 15: May 1 - 15 (2 week window, 2 days in between)
Apr 20: May 10 - 24 (2 week window, 5 days in between)
Apr 23: May 8 - 22 (2 week window, 3 days in between)
Apr 24: car made (got info on May 19)
Apr 25: Just got 'Your Model 3 Final Payment Ready' email, went to account, got the vision agreement and VIN in the source (5YJ3E1EA3NF239xxx)! EDD May 9 - 13
May 10: May 10 - 14
May 11: May 11 - 15
etc...
May 15: went to Tesla Oakville, guy said the car is at their location and after I mentioned that I know about ECU issue he kind of said that the car is waiting for ECU but should be ready by next week
May 19: called tesla, they can't tell me anything new about when, or state of charge; car was built apr 24th, takes around 1.5 to 2 weeks after build date to deliver the car to delivery center
May 30: received 'it's your turn to schedule your model 3 for delivery' text/email, followed link, no appointments available and to check tomorrow and that I'll get a call from SA
May 31: got another text/email 'select your tentative model 3 delivery appointment', followed link, only had 2 choices for Jun 4
Jun 4: Delivery