You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
Someone let me know when I should start dropping by daily to see if it's open
Could you tell which side's wiring was being installed? Primary or secondary?
Someone said Tesla has to come test it. I assume that'd be sometime next week.
Could you tell which side's wiring was being installed? Primary or secondary?
Secondary. It was already connected at the meter side in the cabinet, and they were pulling/connecting the cable to the transformer secondary. Because the current is less on the primary side of the transformer at 12kV, you don't need cable that large. The load on the primary might be 75 amps or so at 12 kV at this site...
The crew was working on the secondary cabling, from the transformer to Tesla's main service panel. Appears primary side is already connected.Could you tell which side's wiring was being installed? Primary or secondary?
Way to go SDG&E! For those keeping track, it was about two weeks from project substantially completed to transformer installation. So, looks like neither the contractor, Carlsbad, nor SDG&E dragged their feet.
And assuming it’ll be open soon, it will have been about 5 months from construction start to finish, with an additional 5 months in permitting before construction start.
From what I can find, that facility is fed at both 138kV and 69kV from SDGE's subtransmission network. They have a substation capacity of ~115MVA, so that's quite a lot bigger than even a large supercharger station (2-3MVA).How big do these 12kv transformers go, and at what point does the customer need a substation? I remember visiting San Diego’s fusion research reactor and was impressed that they needed something like a 100 kV feed. And for their experiments they had to convert that down to something silly like a few hundred volts. Huge bus bars!
So 10 months total from permits to open. Is that the norm to be expected for the area? Just curious since there are several others down in that area I will be watching also, like the Del Mar location.Way to go SDG&E! For those keeping track, it was about two weeks from project substantially completed to transformer installation. So, looks like neither the contractor, Carlsbad, nor SDG&E dragged their feet.
And assuming it’ll be open soon, it will have been about 5 months from construction start to finish, with an additional 5 months in permitting before construction start.
Out of curiosity, how big are these SC installations compared to other industrial SDG&E customers? I am thinking that your typical 10 story office building might only have a transformer this big? How big do these 12kv transformers go, and at what point does the customer need a substation? I remember visiting San Diego’s fusion research reactor and was impressed that they needed something like a 100 kV feed. And for their experiments they had to convert that down to something silly like a few hundred volts. Huge bus bars!
There are 12 kV pad-mounted transformers that are larger than this, so from that stand-point, this isn't as large a load as some of the multi-story buildings. Some high-rise residential projects will have a 4,000 amp panel, whereas this is 2,500 amps. I think one of our Distribution experts told me the largest size transformer in our area is 2,500 kVA (this one is 1,500 kVA). Above that, and you'll need to connect to the transmission system (69kV, for example).
Load on a typical Distribution System circuit can run 5-10 MW, so this site could represent 10% of the load on a larger circuit, and 20% of the load on a smaller circuit. Good load factor, though, with the constant charging...
Valet? Am I misinterpreting this or do some SC's have a person there monitoring the flow?