Stopped by today and found someone working on the pedestals. The backs were off all of them. The guy working on them said he was doing a final check. He said it wouldn't be open today, but probably in the next couple of days.
The guy might have been a Tesla employee because he drove a Model S. Then another Model S showed up.
Yeah that's the Tesla tech doing final inspection. Usually they get turned on later that same day barring any problems. He might have been sandbagging by saying that it should be ready in a couple days. Or just didn't want to make any guarantees.
Assuming this opens tmrw, it will be the 500th supercharger to open in the US. How appropriate, given that it is opening in the city where everything was started in the first place
Assuming this opens tmrw, it will be the 500th supercharger to open in the US. How appropriate, given that it is opening in the city where everything was started in the first place
Three contractor trucks all around the supercharger. Kindly asked one of the gentleman working how progress was going.
His response was there are problems with PG&E. Too much power feeding into the station. They are going to have to step it down a bit. He estimates it will probably be another week before it goes online, I suspect due to the likelihood that PG&E will probably have to reinspect the site again after the modifications.
Three contractor trucks all around the supercharger. Kindly asked one of the gentleman working how progress was going.
His response was there are problems with PG&E. Too much power feeding into the station. They are going to have to step it down a bit. He estimates it will probably be another week before it goes online, I suspect due to the likelihood that PG&E will probably have to reinspect the site again after the modifications.
Ugh. Maybe it's going to be delayed like Sunnyvale where they had to install the buck/boost transformers in front of each of the Supercharger cabinets. I don't know why PG&E doesn't have different taps on their transformers so they can deliver the voltage with a tighter tolerance.
Three contractor trucks all around the supercharger. Kindly asked one of the gentleman working how progress was going.
His response was there are problems with PG&E. Too much power feeding into the station. They are going to have to step it down a bit. He estimates it will probably be another week before it goes online, I suspect due to the likelihood that PG&E will probably have to reinspect the site again after the modifications.
Drove by today. There was someone from E-Tech working on it. There was a whole bunch of cable reels sitting by the electronics enclosure. I could not tell if it was high current wire or what.
I can't believe how long this is taking.