Updates from the contractor:
Disconnect switch is being installed. Green tag is expected tomorrow. This means that they will be ready for the utility transformer. He did not know when the transformer was to be installed.
Back pour for the superchargers is to be complete tomorrow.
Asphalt is scheduled for Friday.
Superchargers may go in on Sunday.
Striping (for the stalls) is scheduled for Monday.
View attachment 68475
Wall around the switchgear will be complete next week.
Sounds like the contractor will be done next week. We will have to keep tabs on that missing utility transformer.