Anything new this Monday, 20 April?
Thanks.
No sign of Pedestals, nor a transformer, yet. The picture at Supercharger - San Diego/Pacific Heights (not open yet) - Page 18 showed 6 Supercharger Cabinets on pallets, and this picture only shows 4 Supercharger Cabinets installed. I wonder how many the final install will have.
Looks like all 6 cabinets are installed -- the other 2 are perpendicular to the 4 you mention, just above them... Odd layout though...
Looks like all 6 cabinets are installed -- the other 2 are perpendicular to the 4 you mention, just above them... Odd layout though...
Thanks for the great hi-res picture. Zooming in, one can see quite a few details.
With three steps forward, and perhaps 2 steps back, it is making progress.
Too bad somebody misplaced the island on the upper left.
So, it appears that there is still a fair amount to be done.
Perhaps another month, maybe the end of May if most goes well.
Except for the variance of transformer install, it looks a lot closer than that. If this were a Supercharger in Kansas in an existing parking lot, my estimate would be 1-2 weeks. Of course SDG&E does not nave a stellar record on quick transformer installs; maybe this location will be the exception...
The rest of the parking lot looks complete!
It looks like the construction crew blew the electric supply to the local street lights this morning causing a major traffic jam at 8a... Hopefully that correlates with supercharger progress, though
It looks like the construction crew blew the electric supply to the local street lights this morning causing a major traffic jam at 8a... Hopefully that correlates with supercharger progress, though
Any updates
I predict May 23rd