The meter box is installed, not the meter.
You are correct, it’s the meter box, not the meter.
I should have taken a better shot to make this more clear.
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
The meter box is installed, not the meter.
Hi Jim,The meter box is installed, not the meter.
Thanks.Stopped bye again today. Everything all buttoned up but no meter. Looks like that is all that is needed.
There are no workers,site cleaned up and doors to enclosure locked. There is rope around the site to show not un use. I have no idea if the site has been finaled by the inspectors or if the power company does that when installing the meter.
Thanks.There are no workers,site cleaned up and doors to enclosure locked. There is rope around the site to show not un use. I have no idea if the site has been finaled by the inspectors or if the power company does that when installing the meter.
Stopped by location yesterday on way from St. Cloud to Jupiter to have dinner at Crafty Crab (very fresh Louisiana style seafood, very close to Superchargers). Looks to be getting close, but still no power infrastructure. Two pics uploadedThe interactive map has been updated. It now explicitly shows a West Melbourne planned Supercharger Station for 2017.
Larry
Hi Mike,Stopped by location yesterday on way from St. Cloud to Jupiter to have dinner at Crafty Crab (very fresh Louisiana style seafood, very close to Superchargers). Looks to be getting close, but still no power infrastructure. Two pics uploaded
Stopped by location yesterday on way from St. Cloud to Jupiter to have dinner at Crafty Crab (very fresh Louisiana style seafood, very close to Superchargers). Looks to be getting close, but still no power infrastructure. Two pics uploaded
Thanks.
If you check posting #78 you'll see them digging a trench at a prospective location for where a utility power transformer is likely to be set. Transformers are large green boxes. Do you happen to remember seeing such a box next to the Supercharger enclosure?
Larry
View attachment 263241
Stopped by talked to the crew doing the install took some pics. Tesla side is done waiting on Florida Power to set transformer and meter, could be as long as a month due to backlog from storms.
View attachment 263244
Those needing a place to charge L3 with Chadamo Tesla adapter and have ChargePoint card go to Melbourne City Hall. FREE!
Has anybody had a chance to swing by lately?
Some of those are old photos. Some show that the transformer is missing.Very exciting news. Friends just went by West Melbourne Supercharger and sent us the attached pics. Perhaps, we have lift-off!
View attachment 266804