To bring this thread to closure, we have an appointment on March 30th to pick up our Model X at the Orlando Service Center. That is almost 2 months earlier than the estimate shown (May-Early June) when I placed the order back in February, and less than 2 months from ordering to delivery. So the timeline is/was:
- Order placed Feb 10, estimate is May-Early June
- Confirmed Feb 18 (automated e-mail and MyTesla)
- VIN received Feb 18 (automated e-mail and MyTesla). MyTesla showing April-Early May
- Received e-mail from DS on Feb 22, stating that production was scheduled for March 13th.
- Production started on March 13th according to MyTesla, still showing April-Early May. No automated e-mail received
- Applied for Tesla financing, TD Bank 90% 72 month 1.99% offer received 2 days later and accepted
- Received e-mail from DS on March 23, stating that production had been completed, and that they were expecting the X to be at the center on March 29. MyTesla updated a day later accordingly. No automated e-mail received.
- Delivery appointment set for March 30th!
100D, 6 seats, Midnight Silver, White seats with carbon fiber, HiFi sound, towing, PUP, 20" wheels, EAP/FSD.
@idontknow1, I hope your schedule gets accelerated too, not sure why the big difference, given you ordered a day earlier. Maybe it is the PUP?