DeepBlueMN
2019 AWD Model 3
Drove by today. Small crew still working. All of the pedestal bases are placed. Charging cabinets were still sitting in the parking lot (in original packaging). Looks like all of the conduit is in place now; they were already re-burying some of it. They were currently doing final positioning and securing of the conduit for the 3 charging cabinets. It looks like they are close to ready to pour cement for the charging cabinet base pads (maybe even a pad for the transformer). Pics attached; sorry a couple of them are slightly out of focus as I was in a hurry and didn’t notice my camera focused on the chain link fencing.