Supercharger - Orange Beach, AL

This site may earn commission on affiliate links.

Dirtman16

White TM3 LR RWD; Red MYP 11/30 OD
Jun 14, 2019
230
396
Madison, AL
Looks like a 12 stall Supercharger going in at the Wharf in Orange Beach, AL. Looks like V3 bases. Link to Facebook

Lat/Long are: 30.292239890806496, -87.62709424633567

Closest address is: 4700B Main St Suite 108, Orange Beach, AL 36561

@Pluto

ETA: Meant to put this under, if a mod could move.
 
Yeah sure thing. See attached.

406970549.jpg
393164896.jpg
406803590.jpg
 
Thanks! Those are the V3 concrete bases for the dispenser pedestals (V3 vs V4 concrete bases described here), so this won't be a V4-pedestal site. Of course they could get Magic Docks installed. Just don't expect V4 pedestals.

This is in "The Wharf" retail complex, and I believe that's the seasonal ice rink in the background of the shots, next to the Sand Dollar Lifestyles store. So the map marker / lat-long above appears correct.

Half a mile to the east, a (non-Tesla) DCFC site is planned at a Cumberland Farms convenience store. The state development agency (ADECA) issued a grant for it back in November 2022, and the latest I heard is that it was in the design and permitting stage. I have no doubt that this Tesla site will be completed first -- that other site might be done by next spring if we're lucky :) Updates here: Cumberland Farms Convenience Store (Coming Soon) | Orange Beach, AL | EV Station
 
Last edited:
We have some progress at the Wharf. There are 12 V3 chargers installed next to the ice rink along with 10 Tesla Level 2 chargers across Wharf Lane. Looks like most hardware is installed with exception of a utility transformer.
 

Attachments

  • IMG_5641.jpeg
    IMG_5641.jpeg
    489.6 KB · Views: 83
  • IMG_5640.jpeg
    IMG_5640.jpeg
    342 KB · Views: 84
  • IMG_5639.jpeg
    IMG_5639.jpeg
    564.9 KB · Views: 76
  • IMG_5638.jpeg
    IMG_5638.jpeg
    449 KB · Views: 73
  • IMG_5636.jpeg
    IMG_5636.jpeg
    585.6 KB · Views: 75
A little progress from last week. The parking area has been resurfaced and lines painted on the supercharger side. Still waiting on the utility transformer. The charger install looks complete on the level 2 side but lacks resurfacing, utilities.
 

Attachments

  • IMG_5663.jpeg
    IMG_5663.jpeg
    560.8 KB · Views: 92
  • IMG_5662.jpeg
    IMG_5662.jpeg
    742.9 KB · Views: 68
  • IMG_5661.jpeg
    IMG_5661.jpeg
    865.3 KB · Views: 68
  • IMG_5660.jpeg
    IMG_5660.jpeg
    600.8 KB · Views: 70
A little progress from last week. The parking area has been resurfaced and lines painted on the supercharger side. Still waiting on the utility transformer. The charger install looks complete on the level 2 side but lacks resurfacing, utilities.
Update from Orange Beach. We visited the Wharf on Jan15. White transformers are in place. Everything looks read to turn on. I can only imagine connection to the Utility or an electrical inspection or both. I don't know why anyone would use the L2 chargers unless they are free.
 
  • Like
Reactions: Jeff Hudson
The white cabinets are not "transformers" per se, rather Tesla's power conversion cabinets. The utility transformer will be a large green or grey cube, and the EMPTY pad for it can be seen in the previous post's photos. Is the utility transformer there yet?

Level 2 stations allow for longer charging sessions. So if you are going to be there for an hour or more, and don't need a full charge, you can avoid idle charges (or having to come back to unplug and move) by just using the Level 2. Cost should be trivial.
 
  • Like
Reactions: Jeff Hudson
Utility Transformer is installed for the Supercharger side along with a transformer on the level 2 side. There is still a set of conduit coming out of the ground on the level 2 side. Parking lighting not complete, there are still empty bases waiting for light poles.
 

Attachments

  • IMG_5695.jpeg
    IMG_5695.jpeg
    567.3 KB · Views: 71
  • IMG_5696.jpeg
    IMG_5696.jpeg
    625.5 KB · Views: 58
  • IMG_5697.jpeg
    IMG_5697.jpeg
    607.9 KB · Views: 57
  • IMG_5698.jpeg
    IMG_5698.jpeg
    424.4 KB · Views: 56
Hi, Progress at The Wharf in Orange Beach. 5 lamp posts are now mounted on their bases. A large spool of heavy gauge wire has disappeared and looks to be installed in underground conduits. Two new panels are now standing one one the Level 2 side and another on the Supercharger side. Each are holding up Meter panels with empty slots for the Utility Meters. Packaging and pallets have been removed. The place looks very close to ready pending a visit by the Utility and final inspection. Sorry no pictures it was getting dark and the place was filling up for a kiddy Mardi Gras parade.