Open date still in 2018????
So long as there is no big delay in getting the utility transformer installed and everything energized, then it should certainly be operational before year end. When talking to planning/zoning boards, Tesla says that they generally expect the construction phase to last 3 to 6 weeks. But timing/scheduling with the utility and transformer procurement is always a bit of a crap shoot, so even if they are basically done being built they could end up having to wait months until things are actually finished.
 
Last edited:
Status as of this morning is: they are working on a Saturday, pad and foundation concrete poured and curing, steel post in place for the fencing and large boxes in the enclosure which may be the charging structures (only a guess). Here are a couple of pictures.
20181117_093440.jpg
 

Attachments

  • 20181117_093434.jpg
    20181117_093434.jpg
    672 KB · Views: 57
Based on the conduit sets, to me it looks like 6 Supercharger Cabinets for 12 stalls (or potentially, though much less likely, 11 stalls). Though I guess it's also possible that they've installed extra conduit to allow for future expansion and there'll actually be fewer installed initially. But, regardless, we should see definitively pretty soon.