The resealing/line painting will likely occur as part of similar work needing to be done at several new supercharger sites under construction in the region.
The resealing/line painting will likely occur as part of similar work needing to be done at several new supercharger sites under construction in the region.
Unlikely - the Lawrence site was finished first. I don't think there have been any photos shared of Salem with the pavement resealed and striped. I think there are a bunch of sites waiting for this finishing touch that needs warmer and dry weather conditions seal & stripe. I guess what we don't know is will Tesla open a site prior to this work being done or not. Because there are a boatload of sites waiting for Tesla to visit right now to commission!
I had a chance to take a look at the meter today, and unfortunately, it is not live. So it appears there is at least one or more further steps by National Grid before Tesla can come commission the site ....
Yes - those are the original chargepoint markings. The contractor hasn't sealed & striped the site yet - waiting for weather conditions to support doing so.
The old lines have been removed and new lines painted. Interesting, they placed the pedestal more towards the middle, probably to try to mitigate non Tesla cars a bit…
The old lines have been removed and new lines painted. Interesting, they placed the pedestal more towards the middle, probably to try to mitigate non Tesla cars a bit…