I went to look at the site for the Parsippany Supercharger and found nothing there. Spoke to the employees and they said that they added diesel and that took the space a supercharger would have. Called town hall in Parsippany and they said no permit has been applied for by Tesla to build a supercharger in Parsippany.
Well an application could be withdrawn, so Wawa certainly could have decided to go diesel instead. But the town hall is confused considering this is public
http://www.parsippany.net/AgendaCenter/ViewFile/Minutes/_04042018-83
http://www.parsippany.net/AgendaCenter/ViewFile/Minutes/_04182018-87
It literally states this was resolved and the following
Application 18:05 Tesla, Inc., 350 New Road, Block: 767 Lot: 29.2 Zone: LIW-2
‘C’/‘D’/Preliminary and Final Major Site Plan to install an electric charging station located at the Wawa site.
A motion to Adopt was made by Mr. Berkowitz, Second by Mr. Reddy.
Approved by Berkowitz, Joskowitz, Persaud, Reddy, Shah, Willans.
Stopped by this location today and saw a bunch of construction. Spoke with the foreman and he said he was working on a gasoline project and not electric. See #1 in screenshot below.
View attachment 331997 View attachment 331998
I'd venture to guess that they'll be constructing the Supercharger in the "Employee Parking" section, which is currently paved with about 10+ parking spots:
View attachment 331999
It's not going into that section nor where the diesel construction is. The minutes also spell out where it's going.
The eight spaces will be located in eight existing spaces behind the fuel canopy parallel to Edwards Road. Two of the eight spaces will be dedicated to Tesla only with the other six shared with Wawa.
That means it's the spots right along Edwards road. The only other spots parallel to it and behind the fuel canopy would be at the Wawa it'sef; but there are only 7 spots there.
Last edited: