ChargeFox Ultra Rapid Network (350kW/HPC)

Discussion in 'Australia' started by Chuq, Oct 3, 2018.

  1. RareEarth

    RareEarth Member

    Joined:
    May 30, 2019
    Messages:
    101
    Location:
    NSW Far South Coast, Australia
    Was at Gundagai the other day, the Chargefox site looks very sad. A couple of buckets covering the cable ducts where the HPCs were, water running out. One of the posts on Plugshare mentions problems with groundwater. Lets hope they fix it soon, it is not a good look.

    Regarding the NeverEnding Story of Cooma, apparently they are still saying the power utility is the hold up.
     
    • Like x 1
  2. QBN_PC

    QBN_PC Member

    Joined:
    Feb 11, 2020
    Messages:
    158
    Location:
    Queanbeyan
    Whenever that power company line gets used, it’s hilarious. The site at Cooma is literally in the car park of the power company’s promo centre.
     
    • Like x 2
  3. jamesgo

    jamesgo Member

    Joined:
    Nov 18, 2019
    Messages:
    200
    Location:
    Australia
    Anyone know why the Chargefox app shows this against the 350kw Ultra rapid chargers?

    upload_2020-11-14_13-27-44.png
     
  4. Candleflame

    Candleflame Active Member

    Joined:
    Mar 9, 2015
    Messages:
    2,234
    Location:
    QLD, Australia
    how can you get an rfid for chargefox chargers?
     
  5. moa999

    moa999 Member

    Joined:
    Mar 4, 2020
    Messages:
    381
    Location:
    Sydney, AUS
    RFID - Chargefox
     
  6. Candleflame

    Candleflame Active Member

    Joined:
    Mar 9, 2015
    Messages:
    2,234
    Location:
    QLD, Australia
    Does this work on QESH 50kw chargers?
    I have been stranded in Carmila before because there was no phone signal...
     
  7. Hairyman

    Hairyman Member

    Joined:
    Jul 24, 2019
    Messages:
    596
    Location:
    Australia
    I've only used NSW sites, but the RFID card works for chargers with a Chargfox Logo regardless of the owner.
     
  8. erosco

    erosco Member

    Joined:
    Oct 24, 2017
    Messages:
    17
    Location:
    Cairns, Australia
    I have a colleague who has one - used it at the Pier in Cairns.. worked!
     
    • Informative x 1
  9. jason66

    jason66 Member

    Joined:
    Aug 27, 2019
    Messages:
    154
    Location:
    New Farm 4005
    Hey chargefox

    Have you considered providing RFID via the passes section in Google pay? If Woolies can do it surely it can't be that hard?
    I find RFID easier than app but don't like to have to use and store a physical card. I know #firstworldproblems
     
    • Like x 4
  10. cafz

    cafz Member

    Joined:
    Jul 17, 2020
    Messages:
    152
    Location:
    Australia
    Good idea, but maybe email it to [email protected] ?
     
  11. meloccom

    meloccom Moderator Aus/NZ

    Joined:
    Feb 11, 2008
    Messages:
    2,278
    Location:
    Sydney Australia
    And whilst they’re at it the same functionality in the Apple Wallet on iOS devices. If ChargePoint can do it surely ChargeFox can.
     
    • Like x 1
  12. RareEarth

    RareEarth Member

    Joined:
    May 30, 2019
    Messages:
    101
    Location:
    NSW Far South Coast, Australia
    Apparently the covers are off the chargers in Cooma!
     
    • Like x 1
  13. moa999

    moa999 Member

    Joined:
    Mar 4, 2020
    Messages:
    381
    Location:
    Sydney, AUS
    Well over 13months since the chargers were installed.
    Nothing shown on Chargefox app
     
  14. Candleflame

    Candleflame Active Member

    Joined:
    Mar 9, 2015
    Messages:
    2,234
    Location:
    QLD, Australia
    the issue is usually a miscalculation of how to get enough power to the site. I.e. Evie guarantees 2 chargers with 350kw, so that means the site needs 700kw. Thats usually not possible without extra power lines so they have to be installed first.
    We all know that no car will be able to draw 350kw yet so they could open the site with reduced power but unfortunately they dont think like that. Power supply can take 6-12 months to install.
     
  15. Anubis

    Anubis Member

    Joined:
    Aug 4, 2019
    Messages:
    229
    Location:
    Sydney
    That's sooo funny.... :)
    The chargers are actually on the Snowy Hydro head office land.
     
    • Funny x 2
  16. Onshore

    Onshore Member

    Joined:
    Mar 8, 2020
    Messages:
    95
    Location:
    SYD
    Ironic since it’s at the HQ for the Snowy Hydro power company!
     
  17. Candleflame

    Candleflame Active Member

    Joined:
    Mar 9, 2015
    Messages:
    2,234
    Location:
    QLD, Australia
    youd think that but these people sit in their planning offices seeing the plan for a 2 stall small EV charging stations. But they have no concept how much power is actually needed. They assume that its enough to recharge car 12V battery.
    Yes, the engineers know but they arent the ones involved in sites and approval of charging locations.

    This was what caused the 6 month delay with the Townsville Evie charger. They built this new Truckstop centre on the outskirts of town. "well equipped with all the power you need". They then realized that the whole truckstop power use (plus small industrial area around it) is completely insiginifcant to the close to 750kw overhead the evie station needed so they had the go back to the main supply lines and run seperate power lines. This of course needs seperate approval again etc.
     
    • Like x 3
  18. cafz

    cafz Member

    Joined:
    Jul 17, 2020
    Messages:
    152
    Location:
    Australia
    Are we sure the covers didn't just disintegrate from age?
     
    • Funny x 7
  19. cafz

    cafz Member

    Joined:
    Jul 17, 2020
    Messages:
    152
    Location:
    Australia
  20. RareEarth

    RareEarth Member

    Joined:
    May 30, 2019
    Messages:
    101
    Location:
    NSW Far South Coast, Australia
    IMG_20201122_132135.jpg
    Cooma this arvo, RH 350kW showing 'out of order'. Other two seem OK although Plugshare user reports that the app won't activate them yet.
     
    • Like x 1

Share This Page

  • About Us

    Formed in 2006, Tesla Motors Club (TMC) was the first independent online Tesla community. Today it remains the largest and most dynamic community of Tesla enthusiasts. Learn more.
  • Do you value your experience at TMC? Consider becoming a Supporting Member of Tesla Motors Club. As a thank you for your contribution, you'll get nearly no ads in the Community and Groups sections. Additional perks are available depending on the level of contribution. Please visit the Account Upgrades page for more details.


    SUPPORT TMC