David Rhee
Member
Stopped by this evening. It's still not active. I had to take a detour to W. Hartford SC to charge...
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
Is this dragged out process a MA "thing"? The Sagamore SC was completed a whole month before they got the clearance to turn it on.
FWIW, these sites are with two different utilities. Sagamore is in the NStar service territory, whlie Auburn is served by National Grid.Is this dragged out process a MA "thing"? The Sagamore SC was completed a whole month before they got the clearance to turn it on.
Is this dragged out process a MA "thing"? The Sagamore SC was completed a whole month before they got the clearance to turn it on.
Well, this should get your hopes up. There is a very large 480 volt generator on a trailer, parked in front of the fence, with cables running in to the chargers/distribution bid. Pics when I get home. It's not running, and there's no one here, but obviously testing is to begin soon. Guessing that must happen before transformer is turned on? Should be live soon.