I-95:
From: Woburn, MA (Permit) - 7.4 miles
To: Seabrook, NH - 31.3 miles
Diversion: 0.8 miles
From: Mansfield, MA - 52.9 miles
From: Dedham, MA - 33.2 miles
To: Kennebunk, ME - 71.4 miles

Another Supercharger to help people avoid Boston, MA.
 
  • Like
  • Informative
Reactions: chjch and mociaf9
Fence is up and cutting away pavement where the pad will go.
 

Attachments

  • D7F4EF21-369E-4837-9264-3E7009D998F8.jpeg
    D7F4EF21-369E-4837-9264-3E7009D998F8.jpeg
    598.2 KB · Views: 193
  • B3E96273-485A-4FA8-B06F-24D943AD2E6F.jpeg
    B3E96273-485A-4FA8-B06F-24D943AD2E6F.jpeg
    631 KB · Views: 167
Trenches are dug and equipment starting to show up. Supercharger nerds help me out here - I think we’re looking at the AC/DC switches here? At first glance I was hoping they were the V3 cabinets that have vents on the top instead of hood on the back but they’re not :( either way this project is moving quickly.
 

Attachments

  • B7C675FF-D739-41E9-9A1F-77D964A5D7E6.jpeg
    B7C675FF-D739-41E9-9A1F-77D964A5D7E6.jpeg
    540.2 KB · Views: 153
  • F8650975-645B-4AA4-8FAA-0EE4A2A75066.jpeg
    F8650975-645B-4AA4-8FAA-0EE4A2A75066.jpeg
    621.5 KB · Views: 146
  • 6092AE58-56B8-42DC-972B-40A6AC65E524.jpeg
    6092AE58-56B8-42DC-972B-40A6AC65E524.jpeg
    546.2 KB · Views: 120
  • BDD2AE3A-AB3E-4101-AB42-FC0E34E2882B.jpeg
    BDD2AE3A-AB3E-4101-AB42-FC0E34E2882B.jpeg
    639.4 KB · Views: 148
  • F3EB136A-0637-42A5-A7B6-30D4A1526B36.jpeg
    F3EB136A-0637-42A5-A7B6-30D4A1526B36.jpeg
    649.7 KB · Views: 145
  • 84CB4460-7168-4E0A-9F87-15F50DD9E6AB.jpeg
    84CB4460-7168-4E0A-9F87-15F50DD9E6AB.jpeg
    446.3 KB · Views: 136
  • B023323A-ED44-4CFF-8BCF-1197D18149FF.jpeg
    B023323A-ED44-4CFF-8BCF-1197D18149FF.jpeg
    689.5 KB · Views: 136
Trenches are dug and equipment starting to show up. Supercharger nerds help me out here - I think we’re looking at the AC/DC switches here? At first glance I was hoping they were the V3 cabinets that have vents on the top instead of hood on the back but they’re not :( either way this project is moving quickly.

Is there anything on the packaging or slip that says Tesla? Just wondering if it might actually be a different charging station
 
  • Like
Reactions: hcdavis3
Pipes are all in place to house wiring, trenches getting filled back in and pad area being cleared. First few forms have been put in place - looks like we should see concrete getting poured soon. And 12 stalls confirmed.
 

Attachments

  • 45CC22EE-14E1-4BAE-A1C2-787917FFFDB6.jpeg
    45CC22EE-14E1-4BAE-A1C2-787917FFFDB6.jpeg
    625 KB · Views: 129
  • 7DFAF48E-7F61-4FA2-B87F-1BC3056593B7.jpeg
    7DFAF48E-7F61-4FA2-B87F-1BC3056593B7.jpeg
    825.6 KB · Views: 123
  • 84D45452-BF09-4F71-B338-15E52349F977.jpeg
    84D45452-BF09-4F71-B338-15E52349F977.jpeg
    754.3 KB · Views: 122
  • 4D7E365A-8A12-4645-A554-EC9EB585CAEE.jpeg
    4D7E365A-8A12-4645-A554-EC9EB585CAEE.jpeg
    720.6 KB · Views: 123
Pipes are all in place to house wiring, trenches getting filled back in and pad area being cleared. First few forms have been put in place - looks like we should see concrete getting poured soon. And 12 stalls confirmed.
I was there on the site today. The cabinets are on site, and they are standard V2 cabinets. It is pretty safe to assume the power output of the station in this site will be 150kW.
 
More progress placing all forms and rebar for stalls - just waiting on concrete. Trench from cabinets to transformer is dug and pad area is getting its electric piping to connect everything.
 

Attachments

  • D64D1982-FBAC-4EB3-BC24-093B0988BECC.jpeg
    D64D1982-FBAC-4EB3-BC24-093B0988BECC.jpeg
    790 KB · Views: 87
  • A5A2D20C-C2C6-41AE-A01C-CEDC8C028272.jpeg
    A5A2D20C-C2C6-41AE-A01C-CEDC8C028272.jpeg
    856.2 KB · Views: 86
  • B85709F9-CF41-4DF7-84F6-F980F59368B0.jpeg
    B85709F9-CF41-4DF7-84F6-F980F59368B0.jpeg
    699.7 KB · Views: 99
  • Like
Reactions: mociaf9
Not much visual progress over the last week - extending the connection from where transformer will go to the main road took a good deal of time. That trench is now getting filled back in as of today. Fence is up around the cabinets. And a giant spoil of cable arrived today woohoo!

Still no sign of supercharger units themselves.
 

Attachments

  • 86D17FAF-6987-41F2-AFD1-77FC501BC9EC.jpeg
    86D17FAF-6987-41F2-AFD1-77FC501BC9EC.jpeg
    950.6 KB · Views: 139
  • 57405218-1F5D-4F16-985B-D7752D3E29F7.jpeg
    57405218-1F5D-4F16-985B-D7752D3E29F7.jpeg
    861.6 KB · Views: 139
  • 712FD9CB-A3A3-49D6-86D1-14D265219980.jpeg
    712FD9CB-A3A3-49D6-86D1-14D265219980.jpeg
    646.9 KB · Views: 133
  • FCF989CB-58C9-4C04-9852-D851365E1CF8.jpeg
    FCF989CB-58C9-4C04-9852-D851365E1CF8.jpeg
    692 KB · Views: 139