TOUK Google map - Existing and upcoming Superchargers accurate to postcode level plus additional layers for more speculative site locations.
Marker links in the tables below also reference Tesla's map. Note that this is not the same as the in-car navigation database and has some errors and omissions. The crowdsourced Supercharge.info map is generally more accurate.
PlugShare’s supercharger list - Tesla and PlugShare have a unique partnership and all Supercharger locations are locked against edits. Locations in construction are usually ‘hidden’ until Tesla asks for them to be public. It is not unusual for locations to appear ‘live’ on PlugShare a few days before Tesla’s own site has been updated.
Planning authorities for Motorway Service Areas (MSAs) - a list of local authorities responsible for authorising planning applications relevant to each service area. These can be used as a way to researching the history or new plans at a service area.
2022 summary: UK and Ireland Supercharger Site News - 2022 Archive
2023 summary: UK and Ireland Supercharger Site News - 2023 Archive
The tables below list sites under construction and proposed sites with markers on Tesla's map, sorted by Tesla's Target Opening date. Historically, marker information has been approximate in terms of both location and timing and many markers end up being removed. Tesla periodically update target site information; the most recent major updates were in February 2023 and March 2024 (follow links for a summary of the changes).
Additional sites not on Tesla's list are also included: if construction has started they are listed in the first table below, other sites (typically where planning requests have been submitted) are listed separately at the end.
Tesla have a separate list of proposed Service Centres on their website (Tesla Service Centers [sic] in United Kingdom), many of which end up with Superchargers. These are included as additional sites if they are not captured by Tesla's proposed Supercharger list but there is evidence (planning or construction) of Superchargers being installed.
Links in the Supercharge.info Marker column open the supercharge.info map centred on the site location marker. Click the marker for more information.
Marker links in the tables below also reference Tesla's map.
2022 summary: UK and Ireland Supercharger Site News - 2022 Archive
2023 summary: UK and Ireland Supercharger Site News - 2023 Archive
UK (scroll to end for Ireland)
Map references
Supercharge.info map - Detailed site location information for existing and upcoming Superchargers for which there is firm evidence (planning or construction). Click on markers for detailed site information; for recent updates refer to the Changes tab.Get notifications on supercharger.info’s UK changes via https://twitter.com/supercharge_uk (turn on feed alerts) - thanks to @scottrobertson
TOUK Google map - Existing and upcoming Superchargers accurate to postcode level plus additional layers for more speculative site locations.
Marker links in the tables below also reference Tesla's map. Note that this is not the same as the in-car navigation database and has some errors and omissions. The crowdsourced Supercharge.info map is generally more accurate.
PlugShare’s supercharger list - Tesla and PlugShare have a unique partnership and all Supercharger locations are locked against edits. Locations in construction are usually ‘hidden’ until Tesla asks for them to be public. It is not unusual for locations to appear ‘live’ on PlugShare a few days before Tesla’s own site has been updated.
Planning authorities for Motorway Service Areas (MSAs) - a list of local authorities responsible for authorising planning applications relevant to each service area. These can be used as a way to researching the history or new plans at a service area.
Annual summary archive posts
2021 summary: UK and Ireland Supercharger Site News - 2021 Archive2022 summary: UK and Ireland Supercharger Site News - 2022 Archive
2023 summary: UK and Ireland Supercharger Site News - 2023 Archive
Sites opened in 2024
Date opened | Supercharger (Tesla marker) | Supercharge.info map reference | Target opening | Location (target marker location comments) & notes | Ref. |
---|---|---|---|---|---|
09/01/24 | London, UK - Bromley | Bromley, UK | Q1 2024 (on schedule*) | Bromley Civic Centre car park, Stockwell Close. Tesla map marker added April 2022, adjacent to The Glades shopping centre. *Target date changes: Q3 2022 to Q2 2023 (August 2022); Q1 2024 (February 2023). [12 x V4 250 kW] | #6,946 (09/01/24) |
15/01/24 | Gatwick, UK - Gridserve Electric Forecourt | Gatwick - Gridserve Electric Forecourt, UK | Not previously listed | Gridserve Gatwick Electric Forecourt next to Mariott Hotel, Gatwick Airport. [4 x V3 250 kW] | #6,994 (15/01/24) |
07/02/24 | Medway, UK - Eastbound | Medway - Eastbound, UK | Q3 2023 (behind schedule) | Moto M2 Medway Eastbound Services. Tesla Medway Eastbound map marker added February 2023, on westbound side of motorway. [12 x V3 250 kW] 8 of 12 stalls commissioned initially; remaining 4 under covers. | #7,041 (07/02/24) |
08/02/24 | Medway, UK - Westbound | Medway - Westbound, UK | Q3 2023 (behind schedule*) | Moto M2 Medway Westbound Services. *Tesla Rainham became Medway Westbound. Map marker added November 2022 in notional town centre location in Rainham. Target date change: Q4 to Q3 2023 (February 2023). [12 x V3 250 kW] | #7,041 (07/02/24) |
10/02/24 | Kettering, UK | Kettering, UK | Not previously listed* | Barton Hall Hotel, Kettering. *Former Tesla map marker located nearby at Kettering retail park, target date Q3 2022, removed in August 2022. [8 x V4 250 kW] | #7,056 (10/02/24) |
12/02/24 | Ipswich, UK | Ipswich, UK | Q4 2023 (behind schedule) | Anglia Retail park, Ipswich (A14 Jct 53). Original planning application was for 20 stalls in two phases (12 plus infrastructure initially + 8 additional stalls in second phase). Tesla map marker added August 2022 at site location. Target date change: Q1 2023 to Q4 2023 (February 2023). [12 x V4 250 kW] | #7,070 (12/02/24) |
14/03/24 | Frankley, UK - Southbound | Frankley - Southbound, UK | 2024 (on schedule*) | Moto M5 Frankley Southbound Services. Tesla map marker added February 2023 at site location. *Target date change: Q3 2023 to 2024 (March 2024) [16 x V4 250 kW] | #7,167 (14/03/24) |
20/03/24 | Bristol, UK - Eastgate | Bristol - Eastgate, UK | Q3 2024 (ahead of schedule*) | Eastgate Retail Park, Eastville, near M32 Jct 32. Tesla map marker added August 2022 in apparently notional location on Bath Road/Keynsham bypass. Originally labelled Bristol East / Bristol Eastville. *Target date change: Q1 2023 to Q3 2024 (February 2023) [8 x V4 250 kW] | #7,210 (20/03/24) |
26/03/24 | Solihull, UK - Service Centre | Solihull (SC), UK | Q1 2024 (on schedule) | Tesla Solihull Service Centre. [6 x V4 250 kW] | #7,260 (26/03/24) |
27/03/24 | Annesley, UK | Annesley, UK | Not previously listed | Mour Hotel, Annesley, near M1 Jct 27 [10 x V4 250 kW] | #7,274 (27/03/24) |
29/03/24 | Larkhall, UK | Larkhall, UK | Q1 2024 (on schedule) | Radstone Hotel, Larkhall, near M74 Jct 8. Corresponds to Tesla "Hamilton" map marker added February 2023 in nearby location. [16 x V4 250 kW] | #7,276 (29/03/24) |
09/05/24 | Gloucester Northbound | Gloucester - Northbound, UK | Not previously listed | M5 Gloucester Northbound Services. [8 x V4 250 kW] | #7,468 (09/05/24) |
09/05/24 | Gloucester Southbound | Gloucester - Southbound, UK | Not previously listed | M5 Gloucester Southbound Services. [8 x V4 250 kW] | #7,468 (09/05/24) |
10/05/24 | Penhale, UK | Penhale, UK | Not previously listed | Kingsley Village Retail Park, Penhale (just off A30) (formerly labelled "Fraddon" on TMC and supercharge.info). [8 x V4 250 kW] | #7,480 (10/05/24) |
29/05/24 | Exeter, UK - Service Centre | Exeter - Exeter Service Centre (SC), UK | Not previously listed | Tesla Exeter Service Centre. [12 x V4 250 kW] | #7,608 (29/05/24) |
14/06/24 | Birch, UK - Eastbound | Birch - Eastbound, UK | 2024 (on schedule*) | Moto M62 Birch Eastbound Services Tesla map marker added Jan 2021, removed April 2021, reinstated in April 2022. *Target date changes: Q3 2022 to Q1 2023 (August 2022); Q3 2023 (February 2023); 2024 (March 2024). [12 x V3 250 kW] | #7,689 (14/06/24) |
24/06/24 | Newport Pagnell, UK - Northbound | Newport Pagnell - Northbound, UK | Not previously listed | Welcome Break M1 Newport Pagnell Northbound Services [12 x V3 250 kW] | #7,749 (24/06/24) |
Sites expanded/upgraded/relocated in 2024
Date change effective | Supercharger (Tesla marker) | Supercharge.info marker | Previous Spec | New Spec | Ref. |
---|---|---|---|---|---|
28/02/24 | Birchanger Green, UK | Birchanger Green, UK | 4 x V2 150 kW | 4 x V2 150 kW + 20 x V3 250 kW V2 stalls retained in original location near Days Inn; 20 V3 stalls, including 4 with a pull-through layout, added in main carpark near Starbucks (about 200 m away). | #7,122 (29/02/24) |
15/03/24 | Hopwood Park, UK | Hopwood Park, UK | 16 x V2 150 kW | 16 x V2 150 kW + 20 x V3 250 kW V2 stalls retained; additional V3 stalls added alongside | #7,175 (15/03/24) |
14/05/24 | Thetford, UK | Thetford, UK | 8 x V2 150 kW | 16 x V4 250 kW V2 stalls removed. Long delay before reopening due to power supply issues (V3 stalls installed and removed during site upgrade). | #7,508 (15/05/24) |
15/05/24 | Woodall, UK - Southbound | Woodall - Southbound, UK | 8 x V2 150 kW | 8 x V2 150 kW + 8 x V3 250 kW V2 stalls retained in original location near exit from service area; additional V3 stalls added in main car park. | #7,530 (15/05/24) |
Upcoming Sites from Tesla.com/permits/construction/awaiting commission
The tables below list sites under construction and proposed sites with markers on Tesla's map, sorted by Tesla's Target Opening date. Historically, marker information has been approximate in terms of both location and timing and many markers end up being removed. Tesla periodically update target site information; the most recent major updates were in February 2023 and March 2024 (follow links for a summary of the changes).
Additional sites not on Tesla's list are also included: if construction has started they are listed in the first table below, other sites (typically where planning requests have been submitted) are listed separately at the end.
Tesla have a separate list of proposed Service Centres on their website (Tesla Service Centers [sic] in United Kingdom), many of which end up with Superchargers. These are included as additional sites if they are not captured by Tesla's proposed Supercharger list but there is evidence (planning or construction) of Superchargers being installed.
Links in the Supercharge.info Marker column open the supercharge.info map centred on the site location marker. Click the marker for more information.
Under Construction
Tesla Marker | Supercharge.info Marker | Target Opening | Plans/Permit | Notes | Ref. |
---|---|---|---|---|---|
Abington | Abington | TBC | Expansion | Under construction: area fenced off and contractors on site as of 12/03/24. Foundations for two charge cabinets and 8 (assume V3) stalls in place as of 19/06/24. Fate of existing V2 stalls TBC (switched off for expansion work). | #7,155 (13/03/24) #7,172 (14/03/24) #7,705 (19/06/24) |
Bar Hill | Bar Hill (SC) | 2024 | Greater Cambridge Shared Planning Ref 23/00798/FUL [Granted, subject to conditions, 06/07/23] | 12x V3 supercharger stalls shown on layout plan included with planning application for proposed Service Centre at Bar Hill, NW of Cambridge (A14 Jct 25). Initial groundworks for service centre underway as of 07/04/24. HV cabling being installed as of 16/06/24, (Supercharger hardware not yet spotted). Tesla map marker added February 2023, near Cambridge Airport (about 10 miles from Bar Hill). Target date change: Q1 2024 to 2024 (March 2024). | #5,642 (11/03/23) #6,948 (10/01/24) #7,313 (07/04/24) #7,695 (16/06/24) |
Barnsley - Haigh | The Old Post Office, Haigh | TBC | Barnsley Council 2023/0507 [Approve with conditions, 22/09/23] | Awaiting final commissioning: 12 x V4 at The Old Post Office, Haigh. Construction looks complete as of 28/05/24. Planning application was for a 12 stall supercharger. | #6,102 (08/07/23) #7,588 (28/05/24) |
Burtonwood | Burtonwood, UK | TBC | Expansion | Reportedly being expanded in a similar manner to other recent Welcome Break sites. Details TBC. | #7,457 (07/05/24) |
Birch Westbound (Middleton) | Moto Birch Westbound | Q4 2023* | Rochdale Council [Grant subject to conditions 02/09/20] | Under construction: Foundations for 12x V3 stalls constructed as of 28/05/23 (24 total quoted for eastbound and westbound; 10x V3 and 6 Ecotricity on plans). Initial groundworks (for third party chargers) commenced at the start of October 2021; Tesla contractor on site as of 21/05/23. In Jan 2021 Tesla had two Birch markers with identical locations midway between the separate eastbound/westbound service areas; one marker was removed in April 2021 & reinstated in April 2022 (see Birch Eastbound). Target date changes: Q2 to Q3 2021 (April 2021); Q3 to Q4 2021 (August 2021); marker removed 03-Feb-22, reinstated April 2022 (target opening Q3 2022), removed again in August 2022. *Marker reinstated November 2022 (target opening Q4 2023); removed again on/before May 2023. | #1,582 (29/07/21) #3,668 (08/10/21) #5,876 (21/05/23) #5,894 (28/05/23) |
Bradford | Cedar Court Hotel, Bradford | TBC | Bradford City Council Ref 23/02778/FUL [Granted 20/10/23] | Under construction: 16 x V4 at Cedar Court Hotel, Bradford. Stall bases in place as of 25/05/24, in layout shown in V4 supercharger planning application drawings. | #6,322 (30/08/23) #7,582 (27/05/24) |
Ferrybridge | Ferrybridge, UK | TBC | Expansion | Reportedly being expanded with at least 6 new stalls in addition to existing 12 x V3. | #7,661 (03/06/24) |
Glasgow | Glasgow Service Centre | 2024 | Glasgow Council [“Grant Subject to Condition(s)” - 29/09/20] | Groundworks reportedly underway on 27/11/23. Area fenced off as of 11/04/24 but charging equipment not yet on site. Number of stalls TBC, reportedly 12 x V4. 8 supercharger stalls shown on service centre site plans. Supercharger reportedly delayed site power supply could be upgraded. Tesla map marker added in April 2022. Target date changes: Q3 to Q4 2022 (August 2022); Q4 2023 (February 2023); 2024 (March 2024). | #1,653 & #2,565 (11/12/20) #6,772 (29/11/23) #7,330 (11/04/24) |
Gretna | Gretna - Caledonia Park | 2024 | Dumfries and Galloway Council Ref 23/1025/CLP [Submitted 18/05/23] | Initial groundworks underway as of 13/05/24: construction area fenced off. 16 x V4 supercharger stalls shown on planning application documents for a site at Caledonia Park, Glasgow Road, Gretna, just off the A74 (M). Tesla map marker (original labelled "Gretna - Caledonia Park") added February 2023 close to proposed location. Target date change: Q1 2023 to 2024 (March 2024). | #5,903 (31/05/23) #7,509 (14/03/24) |
Gretna Green | Gretna Green, UK | TBC | Expansion | Awaiting final commissioning: 14 x V3 stalls replacing previous 4 x V2 ones. New stalls, plus 4 charger cabinets, in place (site temporarily offline) as of 13/02/24. Groundworks for additional 11 x V3 stalls alongside old V2 stalls completed by mid Jan 2024. Groundworks commenced as of 23/11/23 and stall foundations in place as of 15/12/23, adjacent to existing V2 stalls. Four charger cabinet bases also constructed. | #6,826 (15/12/23) #7,005 (23/01/24) |
London Gateway | London Gateway Services | TBC | Awaiting final commissioning: 12 V3 stalls at Welcome Break service area. At least three charger cabinets delivered to site as of 21/03/24. Number of stalls TBC (12 estimated, expected to be V3 in line with other Welcome Break developments). | #7,219 (21/03/24) | |
Old Trafford (Manchester - White City) | Manchester - White City Retail Park | 2024 | Awaiting final commissioning: 16 x V3 at White City Retail Park in Old Trafford. Four charging cabinets in place as of 10/05/23, stalls in place as of 21/05/23. Original site page was titled "Manchester, UK - White City". Tesla map marker added November 2022 adjacent to White City retail park. Target date change: Q3 2023 to 2024 (March 2024). | #5,852 (11/05/23) #5,875 (21/05/23) | |
Manchester - Central (SC) | Manchester - Ashton New Road Service Centre | TBC | Manchester City Council 136498/AO/2023 [Approved 03/07/23] | Awaiting final commissioning: 12 x V4 at Tesla Manchester - Ashton New Road Service Centre. Planning drawings included 12 supercharger stalls and 3 charger cabinets. | #6,104 (08/07/23) #6,833 (17/12/23) |
Milton Keynes Service Centre | Milton Keynes Service Centre | TBC | Milton Keynes Council 23/00676/ADV [Permitted 15/05/23] | Under construction: 11 or 12 x V4 at Tesla Milton Keynes Service Centre, Merton Drive, Redmoor. Construction started 26/01/24 according to Supercharge.info, confirmed 05/03/24 on TOUK Twitter; 3 charger cabinets and at least 11 stall foundations in place as of 18/05/24 (reportedly will be V4). 8x V3 chargers shown on site plans for service centre planning application. Former Tesla map marker added in January 2021. Target date changes: Q2 to Q3 2021 (April 2021) then to 2022 (August 2021). Marker removed in April 2022. | #5,714 (30/03/23) #7,559 (21/05/24) |
Preston - South | Holiday Inn Express Preston South | Q1 2024 | Awaiting final commissioning: 15 stall bases counted in car park of Preston South Holiday Inn Express, Bamber Bridge (M6 Jct 29). Tesla map marker added February 2023. | #6,494 (02/10/23) #6,601 (31/10/23) | |
Rugby - Junction One | Rugby Junction One Retail Park | TBC | Under construction: 12 x V4 stalls at Rugby’s Junction One Retail Park. Charger cabinets and stalls on site as of 24/04/24. Stall foundations in place as of 05/06/24. | #7,376 (24/04/24) #7,666 (05/06/24) | |
Sheffield | Meadowhall Retail Park | 2024 | Sheffield City Council Ref 22/02963/FUL [Grant Conditionally 07/12/22] | Awaiting final commissioning: 12 x V3 superchargers plus 6 Pod Point bays shown on planning drawings for Meadowhall Retail Park EV charging application (just down the road from the shopping centre). Groundworks commenced 05/07/23, tombstones in place 18/07/23. Tesla map marker added April 2022 located at Meadowhall shopping centre. Target date changes: Q3 2022 to Q1 2023 (August 2022); Q3 2023 (February 2023); 2024 (March 2024). | #5,061 (11/10/22) #6,086 (05/07/23) #6,172 (18/07/23) |
South Mimms | South Mimms, UK | TBC | Expansion | Awaiting final commissioning: 24 x additional V3 stalls. Equipment on site as of 09/12/23 appears to include 6 charger cabinets and 24 V3 supercharger stalls. Foundations for at least 17 stalls in place as of 04/01/24. | #6,804 (09/12/23) #6,918 (04/01/24) |
Stevenage | Gridserve Stevenage | TBC | Stevenage Council Ref 21/00536/FPM ["Granted" - 08/07/22] | Under construction: Tesla equipment delivered to site and charger cabinet foundations constructed as of 20/04/24 although rest of site is only in early stage of construction. x4 "Branded chargers", likely superchargers (original planning drawings showed 8 stalls, number reduced in subsequent amendment). | #3124 (14/05/21) #6,658 (10/11/23) #7,447 (02/05/24) |
"Coming Soon™" (On Tesla's Map)
Tesla Marker | Supercharge.info Marker | Target Opening | Plans/Permit | Notes | Ref. |
---|---|---|---|---|---|
Guildford | Guildford Service Centre | Q3 2023 | Tesla map marker in an apparently notional town centre location. x8 Superchargers planned for Guildford Service Centre according to a local source. Timing depends on power arrangements. Tesla map marker added February 2022. Target date changes: Q2 to Q3 2022 (April 2022); Q1 2023 (August 2022); Q3 2023 (February 2023). | #3187 (26/05/21) | |
Washington N | Q4 2023 | Moto service area on A1(M). Tesla map marker spotted October 2023 but could have been added earlier in the year. | |||
Portsmouth - West | Port Solent Car Park | Q1 2024 | Portsmouth City Council Ref 23/00732/FUL [Granted 14/08/23] | 12 x V4 supercharger stalls plus 8 destination chargers shown on planning application for Port Solent car park, just off M27 Jct 12. Tesla map marker added August 2022, located at (and initially named after) Port Solent marina. Target date change: Q1 2023 to Q1 2024 (February 2023). | #6,058 (29/06/23) |
Taunton | Q1 2024 | Marker is east of the town, about 2 miles east of M5 Jct 25. Target date changes: Q4 2021 to 2022 (August 2021); Q3 2022 (April 2022); Q1 2023 (August 2022); Q1 2024 (February 2023). | |||
Plymouth | Q3 2024 | Marker location looks notional: in the middle of the city area on the Manadon Roundabout. See also Gridserve Plymouth Centre in table below which is thought to be a separate site. Target date changes: Q3 to Q4 2021 (September 2021); Q2 2022 (February 2022); Q3 2022 (April 2022); Q1 2023 (August 2022); Q3 2024 (February 2023). | |||
Brighton (305252) | Q4 2024 | Tesla map marker added October 2022, in identical location to existing Brighton marker (see below) but with more specific target date. Target date change: Q4 2023 to Q4 2024 (February 2023). | |||
Bangor | 2024 | Tesla map marker added July 2023 (Q2 2023 Supercharger Voting Winner) in notional town centre location. | #6,138 (13/07/23) | ||
Bournemouth | 2024 | Tesla map marker added in March 2024. May be connected to Bournemouth Service Centre or Ferndown Golf Club (see table below) | |||
Bridport | 2024 | Tesla map marker added February 2023 at The Crown Roundabout near Groves Nurseries in Bridport. Target date change: Q1 2024 to 2024 (April 2024) | |||
Brora | 2024 | Tesla map marker added April 2022, at Brora Golf Club just off the A9 in northern Scotland (but may be a notional location). Target date changes: Q4 2022 to Q1 2023 (August 2022); Q4 2023 (February 2023); 2024 (March 2024). | |||
Cannock | 2024 | Tesla map marker added August 2022 in an apparently notional town centre location. Target date change: Q1 2023 to Q2 2024 (February 2023); 2024 (April 2024). | |||
Cardiff | 2024 | Former Tesla map marker, at M4 Jct 32 (Coryton), added August 2022 with Q1 2023 target date, removed in February 2023. Marker reinstated in March 2024. | |||
Faversham | Macknade Farm Shop | 2024 | Swale Borough Council Ref 23/505424/FULL [Permitted 19/06/24] | 16 x V4 supercharger stalls shown on planning application at Macknade Food Hall, Faversham, just off A2 near M2 Jct 7. Planning application submitted 28/11/23, permitted 19/06/24. Former Tesla Faversham map marker added February 2022, target Q2 2023, removed in February 2023. Marker reinstated in March 2024 with 2024 target date. | #6,989 (15/01/24) |
Godstone | 2024 | Tesla map marker added February 2023 at the A22/A25 roundabout east of Godstone. Service centre marker also shown for this location. Target date change: Q1 2024 to 2024 (April 2024). | |||
Hull | 2024 | Tesla map marker added October 2023 (Q3 2023 Supercharger Voting Winner - bonus site) at St Andrews Quay Retail Park. | #6,582 (27/10/23) | ||
Kingston Upon Thames | 2024 | Tesla map marker added February 2023, in notional location west of town centre. Target date change: Q4 2023 to 2024 (March 2024). | |||
Liverpool | 2024 | Tesla map marker added in March 2024. | |||
Peterborough | 2024 | Tesla map marker added January 2024 (Q4 2023 Supercharger Voting Winner - bonus site) at notional location on south side of city. | #6,953 (12/01/23) | ||
Polmont | 2024 | Tesla map marker added February 2023, in notional location near Junction 5 of the M9. Target date change: Q4 2023 to 2024 (March 2024). | |||
Swindon | Swindon Designer Outlet | 2024 | Swindon Borough Council Ref S/23/0775 [Granted 26/09/23] | 16 x V4 supercharger stalls (plus 20 x 22kW fast chargers) proposed for Swindon Designer Outlet Car Park North. Tesla map marker in town centre added February 2022. Moved in April 2022 to a location adjacent to Swindon Designer Outlet. Target date changes: Q3 2022 to Q1 2023 (August 2022); Q1 2024 (February 2023); 2024 (April 2024). | #6,201 (27/07/23) |
Tamworth | 2024 | Moto service area. Groundworks for "electrical dual circuit installation works" adjacent to services commenced in February 2023. As of March 2024 an area of the car park was still fenced off with "coming soon" charging hub signage, but there had been no recent site activity. Tesla map marker added August 2022 at Moto Tamworth services, M42 Jct 10. Target date changes: Q1 2023 to Q4 2023 (February 2023); 2024 (March 2024). | #5,528 (17/02/23) #7,201 (19/03/24) | ||
Wimbledon | 2024 | Tesla map marker added April 2022, at the location of the Centre Court Shopping Centre. Target date changes: Q3 2022 to Q2 2023 (August 2022); 2024 (March 2024). | |||
Stevenage | 2025 | Former Tesla map marker, at A1(M) Jct 7, added August 2022 with Q1 2023 target date, removed in February 2023. Marker reinstated in March 2024. | |||
Thurso | 2025 | Tesla map marker added in March 2024 in notional location in town centre. | |||
Brighton | TBC | A Brighton marker has existed for many years (in 2017-18 the target date was "by end 2018"). Many have dreamed only to see their hopes dashed: be wary of being seduced by unconfirmed rumours in this much longed-for location. A second nearby marker, removed in August 2022, labelled "Brighton Station" suggests a potential site location near the railway station. See also Brighton (305252), above. Target date changed from 2022 to TBC in May/June 2022. | |||
Liverpool East | TBC | Tesla map marker added February 2022 in Broadgreen area near M62 Jct4, close but separate to pre-existing Liverpool marker (removed in April 2022). Target date changed from Q2 2021 to TBC in April 2022. |
Other Proposed Superchargers (Not On Tesla's Map)
Location | Supercharge.info Marker | Target Opening | Plans/Permit | Notes | Ref. |
---|---|---|---|---|---|
Bromborough | Gridserve Bromborough | TBC | Wirral Council Ref APP/21/01568 ["Approve" - 09/02/22] | x8 “Branded chargers”, likely superchargers [Not on Tesla map] Gridserve plans also shown on their Bromborough web page. | #3,486 (12/08/21) |
Gateshead | Gridserve Gateshead | TBC | Gateshead Council [“Granted”- 30/04/21] | x4 “Branded chargers”, likely superchargers [Not on Tesla map] | #2609 (23/12/20) |
Hartlepool | Gridserve Hartlepool | TBC | Hartlepool Council Ref H/2021/0404 [Environmental Impact Assessment Scoping] | x4 “Branded chargers”, likely superchargers [Not on Tesla map] Gridserve plans also shown on their Hartlepool web page. | #5,056 (10/10/22) |
Nevendon | Gridserve Nevendon | TBC | Basildon Council Ref 21/01515/FULL ["Awaiting Decision"] | x4 "Branded chargers" (Tesla supercharger stalls are shown in the proposed visuals submitted with the planning application in October 2021). Gridserve provide more information on their Nevendon web page (Aug 2021). [Not on Tesla map]. | #3,508 (16/08/21) |
Plymouth Centre | Gridserve Plymouth | TBC | Plymouth Council Ref 21/01696/FUL ["Grant Conditionally" 03/12/21] | x4 “Branded chargers”, likely superchargers [Not on Tesla Map]. Assumed to be additional to Tesla's marker (see Plymouth, above). | #3298 (14/06/21) |
Rutherglen | Gridserve Rutherglen | TBC | TBC | Gridserve indicate their intention to submit a planning application on their Glasgow Rutherglen web page (May 2023) including space for x4 "branded chargers", likely Superchargers. | #5,842 (09/05/23) |
Uckfield | Gridserve Uckfield | TBC | Wealdon Council [“Approval” - 16/03/21] | x8 “Branded chargers”, likely superchargers. | #2,533 (07/12/20) #2,797 (04/03/21) |
Yeovil | Gridserve Yeovil | TBC | TBC | Gridserve indicate their intention to submit a planning application on their Yeovil web page (Oct 2021) including space for x4 "branded chargers", likely superchargers. | #3,696 (21/10/21) |
Reading - Eastbound | Moto Reading Eastbound Services | TBC | West Berkshire Council Ref 23/02937/FUL [Received 21/01/24] | Planning application for a 16 stall V4 supercharger in two phases: 6 + 10. Second phase supported by Megapack battery storage. | #7,092 (22/02/24) |
Rownhams | Roadchef Rownhams Northbound Services | TBC* | Test Valley Council [Granted 16/04/21] Update with canopy: 22/00430/FULLS [Granted 24/03/22] | 12x V3 and 12 Gridserve units in planning application. Additional planning for canopy approved March 2022. Subsequent planning application for service building redevelopment in February 2024 casts doubt on project: only 6 charging bays (3 Tesla) are indicated on planning drawings. Groundworks underway in proposed supercharger location as of 18/03/23 but no Tesla equipment on site. *Former Tesla map marker added in January 2021. Target date changes: Q2 to Q3 (April 2021); Q3 to Q4 (August 2021). Marker removed from map 03/02/22. | #6,545 (18/03/23) #7,115 (27/02/24) |
Stafford | Moto Stafford Northbound Services | TBC | Stafford Council 20/32527/FUL [Granted 29/10/20] | x12 Superchargers [Not on Tesla map] Planning expired on 29/10/23. | #2,739 (12/02/21) |
Wetherby | Moto Wetherby Services | TBC | Harrogate Council [Application Permitted 24/11/21] | x12 Superchargers inferred from plans (same layout as other joint Gridserve/Tesla developments). Screening application for expansion to 66 stalls made in October 2023. Groundworks underway as of 02/12/21 for power supply installation; an array of new Gridserve rapid chargers live as of 14/07/22 but no Tesla equipment yet spotted on site. | #3,854 (05/12/21) #4,817 (15/07/22) #6,581 (26/10/23) |
Winchester Northbound | Moto Winchester Northbound Services | TBC | Winchester City Council Ref 22/02683/FUL [Application Permitted 21/02/23] | Planning application for 12 supercharger stalls plus 12 Gridserve rapid chargers. Former Tesla map marker added August 2022 (on southbound side), marker removed at start of 2023 and link disabled in February 2023. | #5,616 (06/03/23) |
Winchester Southbound | Moto Winchester Southbound Services | TBC | Winchester City Council Ref 22/02730/FUL [Application Permitted 21/02/23] | Planning application for 12 supercharger stalls plus 12 Gridserve rapid chargers. Former Tesla map marker added August 2022, marker removed at start of 2023 and link disabled in February 2023. | #5,606 (05/03/23) |
Annandale Water | Roadchef Annandale Water Services | TBC | Dumfries & Galloway Council Ref 22/0907/FUL ["Grant Unconditionally" 12/08/22] | x9 Tesla plus x10 Gridserve with (?solar) canopies shown on plans for A74(M) J16 service area. Groundworks for Gridserve rapids underway in May 2023. | #4,830 (19/07/22) #5,872 (19/05/23) |
Durham | Roadchef Durham A1(M) | TBC | Durham County Council Ref DM/22/00477/FPA ["Approved" - 20/05/22] | x12 Tesla superchargers + x12 Gridserve with solar canopies shown on plans for A1(M) J61 service area. See also Bowburn, below. | #4,858 (29/07/22) |
Bournemouth Service Centre | Ferndown Service Centre | TBC | Dorset Council (for signage) ["Granted" 31/05/22] | 8x V3 chargers shown on one of the Bournemouth Service Centre site plans in planning application. Former Tesla Ferndown map marker added in January 2021 in location subsequently occupied by (now also removed) Bournemouth marker then moved to a position just off A31 north of Ferndown in April 2022 before being removed in August 2022. Target date changes: Q3 2021 to Q4 2021 (April 2021); Q2 2022 (February 2022); Q3 2022 (April 2022). | #2,660 (06/01/21) #3,900 (21/12/21) #4,069 (31/01/22) #7,255 (25/03/24) |
Bristol - Centaurus Road | Bristol (SC) , UK | TBC | South Gloucestershire Council DOC22/00045 [Decided 15/11/22] | Eight supercharger stalls shown on planning drawings. | #6,103 (08/07/23) |
Lincoln Service Centre | Lincoln (SC), UK | TBC | North Kesteven District Council Ref 23/1199/RESM [Approved 18/01/24] | 8 supercharger stalls shown on plans for service centre at Teal Park, off A46 in Hykeham. | #7,081 (16/02/24) |
Sheffield Service Centre | Sheffield Service Centre | TBC | Sheffield City Council 22/02561/FUL ["Grant Conditionally" 05/09/22] | Planning drawings include 14 supercharger stalls but only two charging cabinets so final number and location TBC. | #4,852 (27/07/22) |
St Albans | St Albans Service Centre | TBC* | St Albans Council Ref 5/2023/2572 [Submitted 18/12/23] [Granted 08/05/24] | 12 x V4 supercharger stalls shown on planning documents for new service centre on Lyon Way, St Albans, AL4 0LQ. *Tesla map marker, target date Q1 2024, added February 2023 at A1(M) Jct 3 (closer to Hatfield than St Albans); marker removed in March 2024. | #7,118 (27/02/24) #7,626 (30/05/24) |
Wolverhampton Service Centre | Wolverhampton (SC), UK | TBC | Wolverhampton Council Ref 23/01125/FUL [Granted 16/02/24] | Planning drawings include 11/12 supercharger stalls for service centre at Mammoth Road, Wolverhampton. | #7,309 (05/04/24) |
Blandford Hill | Blandford Hill Eco Hub | TBC | Dorset Council Ref P/FUL/2021/02622 [“Granted” 26/01/22] | Tesla chargers mentioned on Naturalis Eco Hub development website although not explicitly indicated on planning drawings. | #3,558 (02/09/21) #4,126 (06/02/22) |
Bowburn | Bowburn, UK | TBC | Durham County Council Ref DM/23/02606/RM [Received 29/08/23] | Planning application for a 20 stall supercharger at Integra 61 development, south of Bowburn. Close to Durham Roadchef services which also has a supercharger planning application. | #7,000 (21/01/24) |
Bridgwater | Bridgwater Gateway Business Park | TBC | Developer plans ("detailed planning permission in place") | Business park developer brochure includes a map showing space for Tesla Charging with 8 charging bays. Possibly connected with a former 2021 Tesla marker in Bridgwater town centre (target Q2 2021 in January 2021; 2023 in April 2021; removed August 2021). Note alternative rumours link the former marker to the Gravity business park development; an M5 Moto service area is also nearby. | #3436 (16/07/21) #2696 (21/01/21) #3,436 (16/0721) |
Brierly Hill | Brierly Hill (Port West Retail Park) | TBC | Dudley Council ref P15/1758/C2 [Approved 06/08/21] | x12 supercharger stalls shown on site plan included with planning application for Port West Retail Park, Brierly Hill. | #5,475 (08/02/23) |
Ferndown | Ferndown Forest Golf Club | TBC | x8 stall supercharger reportedly being installed (mentioned in demo day advert). Former Tesla Ferndown map marker added in January 2021 in location subsequently occupied by (now also removed) Bournemouth marker then moved to a position just off A31 north of Ferndown in April 2022 (corresponding to golf club location) before being removed in August 2022. | #6,611 (01/11/23) #7,255 (25/03/24) | |
Leicester - Beaumont Shopping Centre | Leicester - Beaumont Shopping Centre | TBC | Leicester City Council Ref 20231865 [Submitted 29/09/23] | x12 supercharger stalls in planning applications for Beaumont Shopping Centre, Beaumont Way, Leicester. | #7,031 (02/02/24) |
Moffat | Moffat Public Car Park | TBC | Dumfries & Galloway Council Ref 23/0905/CLP [Approved/permission not required 10/07/23] | x8 V4 supercharger stalls shown in supporting statement document submitted with planning application. | #5,845 (10/05/23) #6,182 (22/07/23) |
Newcastle - Holystone | Newcastle - Holystone | TBC | North Tyneside Council Ref 24/00291/FUL [Submitted 12/03/24] | 8-12 V3 supercharger stalls (TBC) indicated in planning application for 37 bay Applegreen EV charging hub. | #7,194 (19/03/24) |
Stranraer | Stranraer (Port Rodie Car Park) | TBC | Dumfries & Galloway Council Ref 23/0739/CLP [Certified as permitted development 18/07/23] | x4 V4 supercharger stalls shown in supporting statement document submitted with planning application. | #5,825 (03/05/23) |
Wakefield | Cedar Court Hotel, Calder Grove | TBC | Wakefield Council Ref 24/00932/FUL [Submitted 30/05/24] | Planning application for 15 x V4 supercharger stalls at Cedar Court Hotel Car Park, Denby Dale Road, Calder Grove, Wakefield, WF4 3QZ | #7,768 (29/06/24) |
Ireland
Map references
Supercharge.info map - Detailed site location information for existing and upcoming Superchargers for which there is firm evidence (planning or construction). Click on markers for detailed site information; for recent updates refer to the Changes tab.Marker links in the tables below also reference Tesla's map.
Annual summary archive posts
2021 summary: UK and Ireland Supercharger Site News - 2021 Archive2022 summary: UK and Ireland Supercharger Site News - 2022 Archive
2023 summary: UK and Ireland Supercharger Site News - 2023 Archive
Sites opened in 2024
Date opened | Supercharger (Tesla marker) | Supercharge.info map reference | Target opening | Location (target marker location comments) & notes | Ref. |
---|---|---|---|---|---|
Coming Soon™... |
Upcoming sites from Tesla.com/permits/construction/awaiting commission
The table below shows proposed sites with markers on Tesla's map, sorted by Tesla's Target Opening date. Historically, marker information has been approximate in terms of both location and timing and many markers end up being removed.Marker | Local Name | Target Opening | Plans/Permit | Notes | Ref. |
---|---|---|---|---|---|
Cashel, Ireland | 2025 | Marker located south of Cashel, near M8 Jct 9. Tesla map marker originally added in August 2022, target date Q1 2023, but removed at the end of 2022. Marker reinstated in March 2024, target date 2025. |