Another update...
PG&E set someone in one of their blue trucks to my house so they could confirm the system was indeed installed as described in the line diagram provided in the NEM2-MT interconnection agreement. This line diagram also matches what the county inspected and approved back in December on the latest permit.
I think (because I can't get straight answers from anyone) is that almost 90 days have passed since the County inspected, they want to make sure I haven't done something to upgrade the system between the inspection and granting PTO. Of course the only reason it's been 90 days since inspection without PTO is because PG&E is super slowwwwwwww.
Anyway; just a heads up to anyone... don't monkey with your system between inspection and PTO since there very well could be a final-final look-over from PG&E.
I get the feeling you specifically are on some list / spreadsheet at PGE and they are like "mwahahaha.... lets keep @!$$%!@#$ with Mr. @holeydonut ..... I know we never send anyone for inspection right before PTO but for THIS guy? Roll the truck!!!!"
Lol.. you are almost there it sounds like.