The cabinets look to be all Tesla and no PSE transformer yet. It looks like the transformer will be located on the other side of the parking lot entrance, a trench between that spot and the Tesla cabinets has already been backfilled and patched. In addition to the PSE transformer it looks like there will be two spare equipment vaults for future expansion beyond the current 8 yet to be energized plinths. The work seems to be paced by relocation of gas and water lines ( behind the shipping container, where transformer is to be located). Well informed source says the gas line relocation will take at least another two weeks then I imagine more inspections then a bit of time for PSE to show up. So I’m guessing best case would be sometime in late July or August. But I’m guessing on that last date.