Not necessarily. There are a zillion variables that influence when a SC gets built, at what speed, etc. One factor is the property leasing arrangement. Every one of those must be negotiated, and it may be that Target doesn't even own the property, they may just lease it from someone else, which means another party has to get involved. Then there's permitting and so on...
So, the progress of one SC usually doesn't have much influence on the progress of another.
Fair enough.
I agree too many variables.... however, in this case the permits for Minnetonka and Minneapolis are already there...
And in some cases the completion of one supercharger has been indicating the next one is about to start... for example Alexandria finally finished.. and then suddenly St. Louis park construction starts up.
And similarly as they deployed these v3 superchargers across the transcanada highway... that same pattern seemed to happen.
So I’m hopeful the next TC ones will start soon... but you’re right, could be many other factors